Steam-water boiler house for the “Complex for producing and processing of poultry (turkey)” in Pervomayskiy district, Tambov region |
Steam boilers ICI Water boilers ICI Joint burners Baltur |
3х5TPH 2х3,5 МW |
«Tambov Turkey»LLC (CHERKIZOVO GROUP) | Pervomayskiy district,Tambov region | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Building of the plant-wide installation of water treatment for the “Complex for producing and processing of poultry (turkey)” in Pervomayskiy district, Tambov region | HTE | 100 m3/h | «Tambov Turkey» LLC (CHERKIZOVO GROUP) | Pervomayskiy district, Tambov region | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Technical re-equipping of the boiler house «Wimm-Bill-Dann» Tsaritsyno» JSC,address: Moscow, 1st Warsaw proezd, 6.,with boiler installation BOSCH TypeUniversal UL-S, steam production 16 TPH |
Steam boilers Buderus Gas burners Saacke |
1х16 TPH |
«Wimm-Bill-Dann» LLC TsaritsynoArea PEPSICO RUSSIA |
Moscow | Engineering, working-out of conceptual solution, fitting of basic equipment, designing |
Steam hot water boiler house for the project "Pig-breeding complex with a complete production cycle of 270 thousand pigs per year" and "Slaughterhouse with refrigerators" at Bezhetsk district, Tver region |
Steam boilers Buderus Hot water boilers Buderus Joint burners Saacke |
2х4+1x8TPH 1х6,5 МW |
«Corall» LLC | Bezhetsk | Fitting of basic equipment, supply of basic equipment, designing, supply of auxiliary equipment, installation, commissioning |
Steam hot water boiler house for the project "Pig-breeding complex with a complete production cycle of 270 thousand pigs per year" structural subdivision "Factory shop of animal feed " at Bezhetsk district, Tver region |
Steam boilers Buderus Hot water boilers Buderus Gas burnersSaacke |
2х2 TPH 2х1,85 МW |
«Corall» LLC | Bezhetsk | Fitting of basic equipment, supply of basic equipment, designing, supply of auxiliary equipment, installation, commissioning |
Hot water boiler house for the project "Pig-breeding complex with a complete production cycle of 270 thousand pigs per year" structural subdivision "АBК" at Bezhetsk district, Tver region |
Hot water boilers Buderus Joint burners Saacke |
2х730 kW | «Corall» LLC | Bezhetsk | Fitting of basic equipment, supply of basic equipment, designing, supply of auxiliary equipment, installation, commissioning |
Technical re-equipping of the boiler station with installation of burners SAACKE |
Rebuild boiler КВГМ-100 Oil-fired burners SAACKE |
100 MW | «Karel’skiy Okatysh» JSC (Division of mining and smelting company «SEVERSTAL») | Kostomuksha | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Building of the steam hot water boiler house Complex for pig slaughter with capacity of 1529 thousand animals in a year and the Recovery subdivision in Tambov region within the frame ofcapital investment project «Building of the slaughter production with capacity of 1529 thousand animals in Tambov region». |
Steam boilers Buderus Hot water boilers Buderus Joint burners Weishaupt |
2x1,25 TPH 1х820kW 2х730 kW |
Filial branchinTambov CJSC «Upravlenie po stroitel‘stvu № 111» (GROUP OF COMPANIES RUSAGRO) |
Tambov | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Construction of the plant's overall chemical water treatment plant for the needs of Complex for pig slaughter with capacity of 1529 thousand animals in a year and the Recovery subdivision in Tambov region within the frame of capital investment project «Building of the slaughter production with capacity of 1529 thousand animals in Tambov region». | HTE | 100 m3/h |
Filial branch in Tambov CJSC «Upravlenie po stroitel‘stvu № 111» (GROUP OF COMPANIES RUSAGRO) |
Tambov | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Building of 3 hot water boiler houses in Tambov region within the frame of capital investment project «Building of the slaughter production with capacity of 1529 thousand animals in Tambov region». |
Hot water boilers Buderus |
2х38 kW, 2х73 kW, 2х135 kW |
Filial branch in Tambov CJSC «Upravlenie po stroitel‘stvu № 111» (GROUP OF COMPANIES RUSAGRO) |
Tambov | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Technical re-equipping of the boiler station LLC «Kampina» |
Steam boilers LOOS Joint burners Weishaupt |
8 TPH |
«Kampina» LLC (FrieslandCampina) |
Stupino | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Technical re-equipping of the boiler station “SKIM” JSC |
Steam boilers ДКВР 10/13 |
30 TPH | “SKIM” JSC | Moscow | Modernization of the gas area of the boiler house, changeover of boilers ДКВР to hot water mode. Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation |
Building of the steam-hot water boiler house for the needs of the factory of paper production «Pulp Invest» LLC |
Buderus Logano S825L 3700 kW LOOS UNIVERSAL Typ UL-SX 7 500 kg/h |
7,4 МWand 7,5 TPH |
«Pulp Invest» LLC | Kazan | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Building of the overall chemical water treatment plant for the needs of the factory of paper production «Pulp Invest» LLC | HTE | 50 m3/h | «Pulp Invest» LLC | Kazan | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, delivery of auxiliary equipment, installation, commissioning |
Building of the hot water boiler house for the needs of the warehouse complex of Ford service parts |
2хUNICALL ELLPREX 970 kW 1хUNICALL ELLPREX 420 Joint burners F.B.R. |
2,36 МW | «SFCardo» LLC | Moscow | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing |
Steam boiler house in Kazan |
Steam boilers LOOS Gas burners Saacke |
_ | «Cotton Way» LLC | Kazan | Working out of evaluation of technical possibility of joining the steam consumer to the existing steam boiler |
Co-generation plant for the needs of the housing estate «Katushki-Ug», Lobnya, Moscow region |
Jenbacher, Viessmann | _ | GK Morton | Stupino |
Working out of building strategy of co-generation plant for the needs of the housing estate «Katushki-Ug», Lobnya, Moscow region |
Novokuybyshevsk oil refinery (НК «Rosneft») |
Hot water boilers LOOS Joint burners SAACKE |
4x 19,2 MW |
Novokuybyshevsk oil refinery |
Novokuybyshevsk, Samara region |
Engineering, fitting of basic equipment, delivery of basic equipment |
Reconstruction of the steam boiler plant Agromilkplant «Ryazansky» |
Set: steam boiler plant LOOS Gas burners SAACKE Smoke flue Н=38 m |
Producing capacity 12 TPH |
Agromilkplant «Ryazansky» JSC |
Ryazan |
Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, designing, installation, commissioning |
Building of blocks № 14, 15 Novokuznetsk Gas-turbine Thermal Power Plant |
Hot water boilers LOOS Gas burners SAACKE |
Thermal efficiency 24MW |
«Sibirenergo- engineering» CJSK |
Novokuznetsk |
Engineering, fitting of basic equipment, delivery of basic equipment, installation supervision, commissioning of the supplied equipment |
Building of the steam boiler house of the plant Voronezhskie Drozhzhi «Lesaffre» (France) |
Set: steam boiler plant BUDERUS Gas burners SAACKE |
Producing capacity 20 TPH |
«VoronezhskieDrozhzhi» JSC (LESAFFRE Group( |
Voronezh | Engineering, fitting of basic equipment, delivery of basic equipment, installation supervision |
Fitting up of the hot water boiler for the company Grad Moskovsky |
Boiler Loos UT-М Burners Elco |
Thermal efficiency 13,5 MW | «RegionEnergoServis» CJSC | Moscow region, Grad Moskovsky | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery, installation supervision |
Modernization of the steam boiler house «Radiopribor» JSC |
Set: Steam boiler plant BUDERUS Logano SHD 815, inkl. Gas burner ELKO |
Producing steam capacity 5 TPH | «Radiopribor» CJSC | Kazan | Engineering, fitting of basic equipment, delivery of basic equipment, installation supervision, commissioning of the supplied equipment |
Reconstruction of the steam boiler house of the plant «Coca-Cola», Saint Petersburg |
Steam boilers LOOS Gas burners Dreizler |
Producing capacity 5 TPH | «Coca-Cola HBC Evraziya» JCS | Saint Petersburg | Engineering, fitting of basic equipment, delivery of basic equipment, installation supervision |
Power center for glass production «Sital» | Cogeneration unit MWM |
Electric power 4,4 MW |
«Sital» JSC | Bryansk | Engineering, разработкапакетногорешения, delivery of thecogeneration unit in container, installation supervision, startup |
Аutomatic gas boiler-house for the plant «Elektroapparat» |
Hot water boilers Viessmann Vitomax 300 Burners Elco |
Thermal power 30 МW |
«Sberegayuschie Energo Technologii» LLC | Bryansk | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, installation supervision, delivery of auxiliary equipment, installation supervision, startup, supervising |
Аutomatic gas boiler-house with reserve fuel tank farm (diesel). Heat supply of the technology park in regard to high tech |
Boilers ASTEBO Two-fuel burners SAACKE |
Thermal power 152 МW |
State Governmental institution of Nizhny Novgorod region «Center for Regional Development» |
Village Ankudinovka, Nizhny Novgorod |
Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, installation supervision, installation supervision, startup, supervising |
Reconstruction of the gas boiler plant with dismantling of old steam boilers and installation of new |
Boiler ICI GX6000 10 TSH Gas burner Saacke |
Producing capacity 10 TPH |
National food group «Sady Pridon’ya» |
Volgograd region, Gorodishchensky district, village Sady Pridonyya |
Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, installation supervision, delivery of auxiliary equipment, installation supervision, supervising |
Аutomatic gas boiler-house for the heat supply settlement Sel‘co, Bryansk region |
Hot water boilers Viessmann Vitomax 300 Burners Elco |
Thermal power 30 МW |
Bryansk Retail Company | Settlement Sel‘co, Bryansk region | Engineering, working-out of conceptual solution, fitting of basic equipment, delivery of basic equipment, installation supervision, startup |